Dovercourt Road

Project timeline

Reserved matters planning consent granted

January 2024

This planning permission allows us to start construction on site.

Construction starts on site

June 2024

  • Vistry and its contractors start work transforming a disused highways depot into a site into a new neighbourhood. There are many stages to this, and the first is site remediation – ensuring the site is ready for housebuilding.

Remediation works carried out by Soilfix

Summer – Autumn 2024

  • Remediation work is being done by a specialist contractor, Soilfix. This involves some tree and hedgerow removal as per the planning permissions – done in collaboration with expert ecologists.
  • Soilfix will also be removing asbestos from the site, and getting the ground ready for foundations.

Home building starts

Autumn / Winter 2024

After Soilfix has completed remediation work, Vistry will start building new homes

First homes completed

By Spring 2025

  • We’ll keep this updated as construction progresses.
Goram Homes Logo
Certified B Corporation logo
Bristol City Council Logo

© Copyright 2023 | Goram Homes Limited – A Bristol City Council owned company. | All Rights Reserved
Registered in England and Wales No.11597204.

© Copyright 2023 | Goram Homes Limited – A Bristol City Council owned company.
All Rights Reserved | Registered in England and Wales No.11597204.